Wintershall Dea has begun drilling four production wells on the Dvalin gas field in the Norwegian Sea, getting ready for the start of production in 2020. The Dvalin field will strengthen Wintershall Dea’s position as one of the largest gas exporters from Norway.

Production drilling starts on the Dvalin Field in Norway
Photo: Wintershall Dea

Drilling of the production wells from the Transocean Arctic rig is expected to last approximately one year and follows an intense summer of activity around the Wintershall Dea operated Dvalin development.

Since April there has been high activity at the Dvalin field with installation of pipe-lines and the manifold at 400 meters water depth. In August, a 3,500 tonne processing module was completed and lifted on to the nearby Heidrun platform in preparation for receiving gas from the Dvalin field. The field is located 259 kilometers north of Kristiansund in mid Norway.

Dvalin is being developed as a subsea field tied back to Heidrun, which lies some 15 kilometers to the northwest. The four wells will be drilled to a depth of around 4,500 meters.

The design philosophy for the wells has focused strongly on HSEQ, in line with the whole Dvalin project to date. The drilling team aims to maintain the project record of having no serious incidents.

Alv Solheim, Managing Director of Wintershall Dea in Norway, said:

“Dvalin fits neatly into our strategy of supplying gas to the European market through fields and pipelines while ensuring we remain one of the most important gas producers on the Norwegian Continental Shelf. It further demonstrates our capabilities as an efficient and capable operator.”

About Dvalin

The Dvalin gas field in the Norwegian Sea is being developed with four subsea wells, tied back to the Equinor operated Heidrun host platform. The gas from Dvalin will be transported to the Heidrun platform via a 15-kilometre pipeline. From there, it will be sent to the Polarled gas transportation system via a 7.5-kilometre pipeline, before it will be further processed to dry gas at the Nyhamna onshore gas terminal. Finally, the gas will be transported via Gassled to the market.