First cross-border offshore wind project on Spanish-Portuguese border announced

The projects will cover a total area of 530 km2, and together the two projects will have an installed capacity of 1.96 GW

First cross-border offshore wind project on Spanish-Portuguese border announced

IberBlue Wind, a joint venture operating in the Iberian market, has announced  two floating offshore wind projects on the North Atlantic coast. They will be located on the border between Spain and Portugal and, have a combined capacity of up to 1.96 GW.

The projects named Juan Sebastián Elcano and Creoula will have approximately 109 turbines and will occupy an area of 530 square kilometers off the coasts of Baixo Miño in Pontevedra and Viana do Castelo. When operational, they will have the capacity to supply electricity to over one million homes. The names Juan Sebastián Elcano and Creoula were chosen for the projects as a tribute to two historic training ships that are part of the Spanish and Portuguese Navy.

The global investment required for the construction and maintenance of the two projects could exceed 4,000 million euros and generate more than 5,000 jobs. These projects represent a pioneering approach to offshore floating wind development that will bring important benefits for both countries. It is estimated that the cost of their joint development could be 32% lower than if they were to be developed separately. This will maximise synergies in resourcing and economies of scale during both the construction phase and operation phases. Consequently, reducing energy prices for both countries, which operate as one within the Iberian Electricity Market – MIBEL.

Adrián de Andrés, Vice President of IberBlue Wind said:

"It is very exciting to develop cross-border floating offshore wind projects and to collaborate with both Portuguese and Spanish governments on this positive opportunity for both countries. We have already engaged with both authorities when we presented our projects to the Spanish and Portuguese authorities, and we look forward to continued engagement."

Juan Sebastián Elcano will consist of 29 wind turbines, of 18 MW each, which gives it a nominal capacity of 522 MW. The wind turbines, installed on floating platforms anchored to the seabed, will extend from As Mariñas to A Guarda, over an area of117 square kilometers. At between 20 and 35 kilometers from the coast, their visual impact will be much reduced.

The location is within the delimitations recently established by the Spanish Government under their Maritime Space Management Plans (POEM), among which is the North Atlantic demarcation, called NOR-1. The project will support local Galician industry which has the ability and experience to undertake this kind of project.

Creoula will have 80 turbines of 18 MW each and an installed capacity of 1,440 MW. The project will cover an area of 413 square kilometers and be between 20 and 40 km from shore.

Creoula is also located within the areas proposed by the Portuguese Government for offshore wind farm development and will contribute to the target set to install 10 GW of offshore wind by 2030.

The construction and operation of both projects will require ongoing collaboration between the developers and many different stakeholders, including civil society, coastal communities and other sea users. IberBlue Wind has already established relationships with port authorities, regional and local administrations, and representative bodies in the two areas, with the aim to positively integrate the projects into the local environments and deliver a sustainable socio-economic opportunity.